Scrum SAFe Advanced Scrum Master (SASM) SAFe-SASM Question # 15 Topic 2 Discussion

Scrum SAFe Advanced Scrum Master (SASM) SAFe-SASM Question # 15 Topic 2 Discussion

SAFe-SASM Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

Lee is a developer on the team. At every daily stand-up Lee reports, "Yesterday, I worked on indexing. Today, I will work on indexing. I have no impediments." What coaching should the Scrum Master provide Lee to improve the team's visibility into his work?


A.

Ask the team to break Lee's Stories into tasks for better understanding


B.

Assign another team member to assist Lee with indexing and ask Lee to start a different piece of work


C.

Tell Lee to pair with another team member


D.

Have Lee discuss his progress in the context of the Iteration goals


Get Premium SAFe-SASM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.