In SAFe (Scaled Agile Framework), lead time is an essential metric used to measure the efficiency and effectiveness of a process. Lead time is defined as the total time it takes for a work item to move through the entire process from the moment it is initiated until it is completed. To measure lead time accurately using a Team Kanban board, two specific timestamps are crucial:
When the Agile Team pulls a Story onto the board (Timestamp C):
This is the starting point of the lead time. It marks the moment when the team commits to working on a particular story by pulling it into the workflow. This action indicates that the story is now in progress and the clock starts ticking from this point.
When the Story is accepted by the Product Owner (Timestamp D):
This is the endpoint of the lead time. It signifies that the story has been completed to the satisfaction of the team and has met the acceptance criteria defined by the Product Owner. When the Product Owner accepts the story, it indicates that the work is done and the lead time measurement stops.
These two timestamps effectively capture the duration a story takes to go through the development process, providing valuable insights into process efficiency and identifying areas for improvement.
SAFe Scrum Master References
SAFe Advanced Scrum Master learning materials
SAFe 5.0 Scrum Master Certification resources
The 2020 Scrum Guide:Scrum Guide 2020
This information aligns with the principles and practices outlined in the SAFe framework and the Scrum Guide, ensuring a comprehensive understanding of lead time measurement within a Team Kanban board context.