Adjusting WIP limits can directly impact Cycle Time and overall flow by reducing bottlenecks and increasing focus. Lowering WIP can enhance the team’s ability to complete work within a Sprint by minimizing task switching and promoting faster delivery of value. References: The Kanban Guide for Scrum Teams.