Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 20 Topic 3 Discussion

Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 20 Topic 3 Discussion

PSK-I Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?


A.

When they want to improve their Cycle Time, flow, and focus.


B.

When there is unplanned urgent work that emerges during the Sprint.


C.

When they see that the average story size they are working on is growing.


D.

When they have extra capacity during the Sprint and want to start some new work items from the Sprint Backlog.


Get Premium PSK-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.