Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 19 Topic 2 Discussion

Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 19 Topic 2 Discussion

PSK-I Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)


A.

Cycle Time scatterplot.


B.

Cumulative Flow diagram (CFD).


C.

Throughput run chart.


D.

WIP Aging chart.


Get Premium PSK-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.