Question #: 2
Topic #: 1

Which techniques should the SAP Activate practitioner follow? Note: There are 3 correct ans-wers to this que-stion.


A.

Optimize testing by running it only at the end of Realize phase


B.

Apply the fit-to-standard first mindset


C.

Reduce business user involvement for efficiency


D.

Leverage dynamic extensibility and integrations


E.

Use agile approach throughout the project