Working in an Agile approach, especially at the beginning of the Realize phase, planning should focus on:
C. User Stories are in Ready state for only the first 2 to 3 sprints.This approach ensures that the team has enough prepared work to start the sprints effectively, but also maintains flexibility to adapt and replan based on feedback and changes from the initial sprints.
This method helps manage the complexity and uncertainty inherent in software development by allowing for iterative assessment and adjustment of work based on team velocity and stakeholder feedback.References:
Agile methodology and Sprint planning practices
Realize phase in Agile SAP projects
Agile Project Planning