SAP Certified Specialist - Project Manager - SAP Activate for Agile Implementation Management E_ACTAI_2403 Question # 1 Topic 1 Discussion

SAP Certified Specialist - Project Manager - SAP Activate for Agile Implementation Management E_ACTAI_2403 Question # 1 Topic 1 Discussion

E_ACTAI_2403 Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?


A.

Leveraging effort estimates for similar User Stories from another Scrum team


B.

Detailed bottom-up estimates that break each User Story into shorter tasks


C.

Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team


D.

Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days