SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2021 Question # 5 Topic 1 Discussion

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing C_TS422_2021 Question # 5 Topic 1 Discussion

C_TS422_2021 Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

Which time elements are part of a routing operation?


A.

Pick/pack time


B.

Float before production


C.

Queue time


D.

Wait time


E.

Move time