A minimum requirement for applying the Business Case theme in PRINCE2 is to define the actions necessary to confirm that the project’s benefits are realized. This involves planning how benefits will be measured and managed both during and after the project to ensure they deliver the intended value and outcomes. References: PRINCE2® 7 Foundation Handbook and official training materials.