The level of management that sets the project level tolerances in PRINCE2® is corporate, programme management, or the customer. These project-level tolerances are defined to set the allowable limits of variation for the project’s objectives, which the Project Manager must work within. This helps ensure that the project remains aligned with strategic goals and customer or corporate standards.References: PRINCE2® 7 Foundation resources and materials.