PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 10 Topic 2 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 10 Topic 2 Discussion

Prince2-Foundation Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

Which level of management sets the project level tolerances?


A.

Project board


B.

Team manager


C.

Corporate, programme management or the customer


D.

Project manager


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.