The advantages of having a clear end to a project include ensuring that no further costs are incurred by the project (1) and that project products are transferred to operations and support for ongoing use (2). The achievement of all benefits at project closure (3) is not guaranteed and typically occurs post-project, and the project brief is not re-baselined at project end (4). References: PRINCE2® Foundation Handbook, Closing a Project section.