During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.

Which practice is being applied through the ‘controlling a stage’ process?


A.

Business case


B.

Organization


C.

Plans


D.

Quality