PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 3 Topic 1 Discussion

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 3 Topic 1 Discussion

PRINCE2-7-Practitioner Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?


A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager


B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf


C.

No, because assurance information may be provided to the project board and not to the business layer


D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects