Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 652 Topic 66 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 652 Topic 66 Discussion

PMP Exam Topic 66 Question 652 Discussion:
Question #: 652
Topic #: 66

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received, demanding that the project be stopped.

What should the project manager do first?


A.

Register the issue and escalate it to the project sponsor.


B.

Execute the contingency plan defined in the risk management plan.


C.

Meet with the project stakeholders to define a mitigation plan.


D.

Estimate the cost of changing the project location.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.