PMP Exam Topic 62 Question 618 Discussion:
Question #: 618
Topic #: 62

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?


A.

Follow the risk management plan.


B.

Reduce the team effort utilization.


C.

Look for cost-saving opportunities.


D.

Submit a change request to add to the management reserve.