An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?


A.

Reduce the projects’ scope to meet the upcoming target dates.


B.

Crash the schedule from the delayed projects to meet upcoming target dates.


C.

Fast-track the delayed projects so they can meet upcoming target dates.


D.

Ask for project sponsor approval to revise the upcoming target dates.