PMI Project Management Professional (PMBOK 7th Version) PMP Question # 614 Topic 62 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 614 Topic 62 Discussion

PMP Exam Topic 62 Question 614 Discussion:
Question #: 614
Topic #: 62

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?


A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep


B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place


C.

Advise the team not to engage in modifications unless it follows the proper change approval process


D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced