Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 611 Topic 62 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 611 Topic 62 Discussion

PMP Exam Topic 62 Question 611 Discussion:
Question #: 611
Topic #: 62

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?


A.

Involve all of the stakeholders in the escalation by setting up a conference call.


B.

Escalate to the other party's management and inform the steering committee.


C.

Reach out to peer managers for similar escalation situations and follow past experiences.


D.

Review the established project escalation process and take the appropriate action.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.