PMP Exam Topic 62 Question 610 Discussion:
Question #: 610
Topic #: 62

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?


A.

Put the project on hold until all definitions are ready in order to avoid rework.


B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.


C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.


D.

Cancel the project release resources, then start again when all the definitions are ready.