PMI Project Management Professional (2025 Version) PMP Question # 609 Topic 61 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 609 Topic 61 Discussion

PMP Exam Topic 61 Question 609 Discussion:
Question #: 609
Topic #: 61

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?


A.

Identified the stakeholders and their expectations


B.

Presented the project to the community


C.

Added this situation to the risk register


D.

Added these requests to the project scope statement