Question #: 609
Topic #: 61

A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.

What should the project manager do to initiate the adoption of agile within the company?


A.

Organize agile workshops with the developers and testers to gain their support in using agile approaches for their projects.


B.

Request that all the project managers and business managers receive training in the agile framework used previously by the project manager.


C.

Advise the PMO manager to continue with the company's current predictive approaches until all the projects in execution are closed.


D.

Assess the organization's culture to determine if agile can be used in project delivery and determine the practices to be used.