PMI Project Management Professional (PMBOK 7th Version) PMP Question # 607 Topic 61 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 607 Topic 61 Discussion

PMP Exam Topic 61 Question 607 Discussion:
Question #: 607
Topic #: 61

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?


A.

Prepare performance value reports for the business on an ongoing basis.


B.

Include demonstrations of the built portion of the product at the end of every sprint.


C.

Prepare a project report for the stakeholders and distribute it weekly.


D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.