PMI Project Management Professional (2025 Version) PMP Question # 607 Topic 61 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 607 Topic 61 Discussion

PMP Exam Topic 61 Question 607 Discussion:
Question #: 607
Topic #: 61

A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

Which first two actions should the project manager perform? (Choose 2)


A.

Create a change request to discuss with the change control board (CCB).


B.

Perform a risk identification process with the project team.


C.

Ask the project sponsor for additional budget for contingency.


D.

Consult with the project stakeholders and evaluate the impact.


E.

Discuss the possible impacts with subject matter experts (SMEs).