Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 606 Topic 61 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 606 Topic 61 Discussion

PMP Exam Topic 61 Question 606 Discussion:
Question #: 606
Topic #: 61

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?


A.

Accept risks as they decrease over a period of time.


B.

Create a risk value profile to track the relative importance of risks.


C.

Log and track risks separately as only business value is important.


D.

Assess risks together with business value during prioritization.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.