Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 106 Topic 11 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 106 Topic 11 Discussion

PMI-ACP Exam Topic 11 Question 106 Discussion:
Question #: 106
Topic #: 11

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?


A.

Plan activities that will require the team to work collaboratively on a regular basis.


B.

Set collaboration metrics and evaluate individuals against those metrics.


C.

Request that line management add more collaborative team members to the team.


D.

Allow the team to continue with no interference as activities are being met.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.