PMI-200 Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?


A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.


B.

Evaluate the team's capacity and help them select user stories for the iteration based on 60% of their capacity utilization.


C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.


D.

Evaluate the team's capacity and help them select user stories for the iteration based on 80% of their capacity utilization.