PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 66 Topic 7 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 66 Topic 7 Discussion

PMI-200 Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

During a review session, an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value.

What should the team have done to prevent this?


A.

Reprioritized requirements prior to committing to iteration work


B.

Ensured that requirements remained stable during the iteration cycle


C.

Had stakeholders focus on items created after the product backlog was initially built


D.

Worked on features rather than a set of components


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.