The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?
Commit to a specific feature set for delivery
Explain that a commitment will be provided after planning
Have the team estimate in story points to commit to a specific set of features
Use the team's historical velocity to calculate a range of features that can be delivered