A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?
A.
Suggest the product owner start by focusing on the next 2 sprints instead of 10
B.
Spend the first few sprints to develop detailed schedules and budgets
C.
Invite the product owner to the retrospective to explain the team's approach to schedule and budget
D.
Explain that detailed project schedules and budgets are not artifacts in agile projects
Chosen Answer: