PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 24 Topic 3 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 24 Topic 3 Discussion

PMI-200 Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

A team using Kanban identifies that their cycle time has significant variation After brainstorming the team determines that the root cause is the stones' varying sizes and risks.

What should the team do?


A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories


B.

Create a triage step on the Kanban board to pre-identify risky stones


C.

Set a policy to break down stories larger than a specified complexity then adjust the WIP


D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.