PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 93 Topic 10 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 93 Topic 10 Discussion

PMI-200 Exam Topic 10 Question 93 Discussion:
Question #: 93
Topic #: 10

An agile practitioner is in the process of refining requirements. The requirements keep changing based upon with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?


A.

Ask the scrum master to help reduce the rate of change.


B.

Work with the agile coach to document the requirements in a collaborative way.


C.

Work with the stakeholder directly rather than go through different layers of people.


D.

Work with the development team to confirm the requirements.