A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?
Engage the team to determine the sprint velocity based on previous agile projects.
Average the sprint velocity based on input from team members
Share the sprint velocity obtained from the sponsor with the team
Run multiple sprints before determining the sprint velocity with the team.