Question #: 91
Topic #: 10

A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?


A.

Assign agile roles within the team and conduct training for each role to provide understanding of the agile methodology.


B.

Organize training and development workshops to help all stakeholders to form a shared understanding of agile practices.


C.

Plan a transformation to agile delivery methods for senior leadership before starting project implementation.


D.

Apply only agile methods and practices for specific deliverables of the work and assign this work to experienced agile team members.