PMI-002 Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

Which of the following subsidiary plan contains the quality objectives for the project?


A.

Quality baseline


B.

Quality management plan


C.

Process improvement plan


D.

QA checklist