PMI-002 Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?


A.

Parametric estimating


B.

Funding limit reconciliation


C.

Reserves analysis


D.

None of the above