PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 150 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 150 Topic 16 Discussion

PMI-002 Exam Topic 16 Question 150 Discussion:
Question #: 150
Topic #: 16

Which of the following are NOT outputs of the Activity Duration Estimation process?


A.

Activity duration estimates


B.

Schedule baseline


C.

None of the choices are correct


D.

Updates to activity attribute


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.