PMI-002 Exam Topic 15 Question 149 Discussion:
Question #: 149
Topic #: 15

An approved change request is an input to which of the following processes?


A.

Define Scope


B.

Verify Scope


C.

Monitor and Control Project Work


D.

Integrated Change Control