When a risk should be avoided?


A.

The risk event has a low probability of occurrence and low impact.


B.

The risk event is unacceptable - generally one with a very high probability of occurrence and high impact.


C.

It can be transferred by purchasing insurance.


D.

A risk event can never be avoided.