A fixed-price-plus-incentive-fee (FPI) contract has a target cost of $130,000, a target profit of $15,000, a target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual cost of the project was $150,000. How much profit does the seller make?


A.

$10,000


B.

$15,000


C.

$o


D.

$5,000