PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 92 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 92 Topic 10 Discussion

PMI-002 Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

A Resource Leveling is a technique for:


A.

Develop Schedule


B.

Estimate Activity Durations


C.

Estimate Activity Resources


D.

Sequence Activities


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.