PMI-002 Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

The amount of time that an activity can be delayed from its early start without delaying the project end date is called:


A.

Negative Float


B.

Total Float


C.

Float


D.

c and b