Scrum is built aroundtimeboxed iterationscalled Sprints, where teams work in a fixed period (typically 1-4 weeks) to deliver a potentially shippable product increment.
A.Incorrect. While Scrum incorporates some Lean principles, its foundation is timeboxing, not Lean.
B.Incorrect. Scrum and DevOps are complementary but distinct. Scrum is not based on DevOps principles.
C.Correct.Timeboxing is a core aspect of Scrum, ensuring focused delivery within a defined timeframe.
D.Incorrect. Scrum rejects sequential (Waterfall-like) processes in favor of iterative and incremental work.
References:
Scrum Guide 2020: Sprints and Timeboxing