Question #: 5
Topic #: 1

During an internal audit, a manufacturer of polystyrene packaging products for the electronics industry found that six per cent of finished products being ejected from the moulding machines fell onto the factory floor instead of into collection baskets. The factory floor was wet and dirty in places, so a lot of products were rejected at inspection. Auditors raised a non-conformity to the Maintenance Manager.

Select three options for the corrective action to be taken by the Maintenance Manager that could be needed to prevent rejects from recurring.


A.

Record every product falling onto the floor as a non-conformity.


B.

Place a worker at the ejection point to place any product falling to the floor into the baskets.


C.

Ask customers to accept dirty products.


D.

Redesign the factory layout to better handle finished products.


E.

Set up a system of regular inspection of the floor condition.


F.

Make staff aware that products are falling onto the factory floor.


G.

Install guides at the point of ejection to better direct products into the baskets.