Which is the correct sequence of possible solutions that a constrained plan might consider when attempting to resolve a capacity or resource overload?
A.
First alternate resources, then substitute components, then alternate work definitions and item structures, and finally, alternate suppliers and source organizations.
B.
First alternate suppliers, then alternate resources, then substitute components, then alternate work definitions and item structures, and finally, alternate source organizations.
C.
First subscribe components, then alternate resources, then alternate work definitions and item structures, and finally, alternate suppliers and source organizations.
D.
First alternate item structures, and work definitions, then substitute components, then alternate resources, and finally, alternate suppliers and source organizations.