1z0-1066-25 Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

Your client has high-priority customers with frequent, small volume orders.

Which two steps should a backlog planner consider if a backlog run does not produce the desired results? (Choose two.)


A.

Edit the "Enforce Current Commit" or "Pull-in Enabled' demand attributes.


B.

Activate more intricate Demand Priority rules.


C.

Isolate the problematic customer in its own Backlog Planning run.


D.

Consider simulation.


E.

Edit the "Pull-in Disabled" demand attribute.