An as built plan review is a type of plan review that may provide information about a modification such as the removal of an abandoned underground flammable liquid tank. An as built plan review is conducted after the construction or alteration of a building or system is completed and before the final approval or acceptance by the AHJ. An as built plan review verifies that the building or system conforms to the approved plans and specifications and complies with the applicable codes and standards. An as built plan review may also identify any changes or deviations from the original plans that occurred during the construction or alteration process, such as the removal of an underground tank.References:
NFPA 1: Fire Code, 2018 Edition, Section 1.12.8.1.11