Question #: 19
Topic #: 2

A ground-mount PV system is planned for a site with a soil bearing capacity of 2000 psf. The array footing design requires a minimum bearing pressure of 1500 psf. What is the safety factor for this installation?


A.

0.75


B.

1.33


C.

1.5


D.

2.0