ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 3 Topic 1 Discussion

ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 3 Topic 1 Discussion

CTAL-TM Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

You are Test Manager on a new project and have estimated the test effort to be 500 days, assuming that you will find no more than 50 defects and 5 test iterations being required. The project manager has said the estimate is too high. Which of the following options could enable you to reduce this estimate?

SELECT ONE OPTION


A.

Agree an increase in the Unit test coverage before the code is delivered to your test team.


B.

Assign more test analysts to the test execution phase.


C.

Increase the regression test coverage.


D.

Allow more time for the developers to fix the defects found.