You are Test Manager on a new project and have estimated the test effort to be 500 days, assuming that you will find no more than 50 defects and 5 test iterations being required. The project manager has said the estimate is too high. Which of the following options could enable you to reduce this estimate?
SELECT ONE OPTION
Submit