CTAL-TM_Syll2012 Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

Testing Process

Which of the following is an example of the test closure activity indicated as "lessons learned"?

Number of correct responses: 1

K21 credit


A.

Archive all the test results of the acceptance testing phase


B.

Deliver a list of the open defects of a software product released into production to the service desk team


C.

Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects


D.

Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing