CTAL-TM_Syll2012 Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

People Skills – Team Composition

Which of the following would you expect to be most likely an example of a demotivating factor for testers?

Number of correct responses: 2

K21 credit


A.

The management asks the testers to be kept informed about the intensity, quality and results of testing


B.

The testers’ recommendations to improve the system or its testability are adopted by the development team


C.

The same regressions tests are manually executed by the same testers, for every product release, without regression test tools


D.

The testers are assessed on whether and how often they detect important and critical failures


E.

Test quality is measured by counting the number of customer/user reported problems.