Isaca Certified in the Governance of Enterprise IT Exam CGEIT Question # 15 Topic 2 Discussion

Isaca Certified in the Governance of Enterprise IT Exam CGEIT Question # 15 Topic 2 Discussion

CGEIT Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

An ongoing project is on track according to project plan. However, a recent regulation change will have a major impact to the project. The project sponsor's NEXT step should be to:


A.

Seek exemption from the appropriate regulatory body


B.

Perform an impact analysis and update the business case


C.

Submit the project to the IT steering committee for reapproval


D.

Rescope the project to remove work impacted by the regulation