GSLC Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

You are the project manager of a large project that will span several time zones. You'll be utilizing project team members from across several departments. Project team members won't be working on the project full-time and will join and leave the project based on assignments in the project schedule.

What project management plan can you create to help you manage when project times will be brought onto and released from the project team?


A.

Staffing management plan


B.

Team management plan


C.

Project management plan


D.

Human resources management plan